The conditional routing by link weight (PackFeed2 - Conveyor22 or Conveyor 23; PackFeed4 - Conveyor26 or Conveyor27) is not working for me. The current file is set to make the decision by initial priority, but I have tried other methods with no success:
> Assign ModelEntity.Priority with addon process, then route by link weight of ModelEntity.Priority=="X"
> Assign link weight by ModelEntity.EntityType
> Assign link weight by ModelEntity.BatchMembers.Contains("X")
I think this may not be working because they are arriving as a parent/member batch. Is there a different link weight condition that may work. Please note I have 1 parent type and 2 member types. The decision needs to based off of the member entity.
The area of concern is towards the end of the process at the top left of the simio (file attached).
APS Design 2.spfx