Jump to content

simultaneous steps in sequence table


Mirek
 Share

Recommended Posts

Hello together,

would be very thankful for any advice:

 

I have a sequence table with sequences according to their workstations:

 A - B - C - D

If I only have one operator, they can just be done one after another.

If I have 2 Operators A and B  can be done simultaneously to C. 

 

How can I model this?

The problem is probably, that the entity (batch) has to be splitted to let workstation A and C run at the same time.

I tried it with process-add-ons like creating a second entity and transfer it to Station C. 

There might be a much easier solution?!

 

Thank you in advance! 

Link to comment
Share on other sites

×
×
  • Create New...