Hello Simio Forum.


I’m just starting a model which, for me, is a little unique as I have only used servers in a task capacity through steps.


The new liquid ink model consists of 4 lines with each line made up of 3 steps each having a volume of 3.5 tonnes.

1. PreMix

2. Mill with a recirc tank

3. PostBlend

I do not seem to be able to model this using servers because I cannot represent the transfer time of product occupancy between steps. I need this to show utilisation/uptime of the steps.


But when I look at using "Flow" tanks I cant add the process tasks the same as servers (rows) i.e. gather weigh, milling time, QC etc.. Plus will need to add/link worker steps.


Is there a middle ground between servers & tanks?


Thanks

Martin

Share this post


Link to post
Share on other sites

Perhaps a middle ground is to use a Server with Task Sequences and then for the tasks you might consider a Process Type of Submodel.

Share this post


Link to post
Share on other sites
Guest
You are commenting as a guest. If you have an account, please sign in.
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.


×