Hi

I've built a very complex add on trigger process but i think it should be simpler, I'm not sure how to do it. I have 5 scheduled maintenance that will be carried out according to the flying hours. The first 60 hours, conduct Cx 1, second 60 hrs conduct Cx 1 but at the third 60 hrs it will conduct Cx 2, and so on. This is basically how the schedule look like.


60 60 60 60 60 60 60 60 60

Cx 1 Cx 1 Cx 2 Cx 1 Cx 1 Cx 2 Cx 1 Cx 1 Cx 3

60 60 60 60 60 60 60 60 60

Cx 1 Cx 1 Cx 2 Cx 1 Cx 1 Cx 2 Cx 1 Cx 1 Cx 4

60 60 60 60 60 60 60 60 60

Cx 1 Cx 1 Cx 2 Cx 1 Cx 1 Cx 2 Cx 1 Cx 1 Cx 3


How should I write the routing logic? Very much appreciate it. Thanks

Share this post


Link to post
Share on other sites

Use as timer which executes a custom process (timer_MTBF.Event).


You may then simplify the MTTR logic within the event driven process.


Hope this helps.