Thank you.
As you said, I tried to make setup work rightly.
So, I make same way with Simbit "WorkstationWithSequenceDependentSetup".
However, I think Simio consider all my entities to Pallet (Parent entity) as there is combiners before going to Workstation.
Because of this, changeover is not working.
How can I solve this problem??
Also, I need to proceed entity with batch as this Machining center make a product 100cs at once.
Therefore, I have to use Combiner.
Moreover, I don't have enough time to finish this modeling. So I asked you many things on a time.
What I mean about question 2 is that I want the number of entities going to Workstation to be variables using property.
So I want to control how many workstations changeover occurs each time I process it.
For example, if 10 of M1s go to workstation and then 10 of M2s go, a change over will occur for every 10. I want to control this number!!!