To limit spam this and all Public Forums have very limited ability to attach files. We recommend that support issues and more technical topics be initiated inside one of the Simio Insider (SI) forums below where you can attach your model and see example solutions. See above Welcome forum to join Simio Insiders.
Post Reply
Kaylinn
Posts: 3
Joined: Fri May 15, 2015 1:35 pm

Process time depending on entity count

Post by Kaylinn » Wed May 27, 2015 11:46 am

Hello! I am modeling a wash station that takes 30 minutes for the first piece, and an additional 5 for each piece after that(so a batch of 3 would take 40 minutes, a batch of 6 would take 55 minutes, and so on) but I'm having some trouble putting this into a processing time. The added problem is that the number of entities changes. Currently I'm using a source that produces one "shipment" a day with "Entities per arrival" set as "random.triangular(3,13,19)" which is working fine for my quantity, but I don't know how to relate that into the processing time of the next workstation.

Thanks!

SEVAR1
Posts: 23
Joined: Tue Jun 11, 2013 11:58 am

Re: Process time depending on entity count

Post by SEVAR1 » Wed May 27, 2015 3:45 pm

Hi Kaylinn,

I built a simple model which I believe does what you need. It might not be the most elegant way to do it but it's pretty simple. I created two state variables (BatchQuantity and PreviousCumulativeQuantity) which dictate the processing time of the server. However, you would need to post your question in the Simio Insiders forum because it's impossible to attach files in here to prevent spam!
Sébastien