Search found 5 matches

by rhamzei
Sun May 24, 2015 4:46 am
Forum: Discussions
Topic: Multitask worker with more than 2 servers and 2 sources
Replies: 2
Views: 3650

Re: Multitask worker with more than 2 servers!

I solved this problem by myself.( I forgot to add to paths from source2 to server3 and from server3 to sink, please make changes and run it):
http://dibadata.com/uploads/WORKER-%203 ... urces.spfx
by rhamzei
Sat May 23, 2015 1:16 pm
Forum: Discussions
Topic: Multitask worker with more than 2 servers and 2 sources
Replies: 2
Views: 3650

Multitask worker with more than 2 servers and 2 sources

HI all! I have a question which I could not handle it! I want to send a worker to do job in server 1, by finishing in server 1, it must go to server2 to do process and then go to server 3 and does its dut. then it must come back to server 1 and wait for starting new process ( worker transfers betwee...
by rhamzei
Thu May 21, 2015 10:23 am
Forum: Discussions
Topic: Running Logic for server
Replies: 2
Views: 3895

Re: Running Logic for server

Thx for your useful reply :)
by rhamzei
Wed May 13, 2015 3:43 am
Forum: Discussions
Topic: Running Logic for server
Replies: 2
Views: 3895

Running Logic for server

I have a server which its initial capacity is 2. But the server (an oven) will start working just when its fed with two entity. It means first entity must be waited in the server till next entity being transferred into. Then the server initiates the process. How can I use this logic ? (The model is ...
by rhamzei
Wed May 06, 2015 12:17 pm
Forum: Discussions
Topic: Assembly Line Modeling
Replies: 0
Views: 6253

Assembly Line Modeling

I want to simulate a solar panel assembly line in simio which produce 2 models, one panel with 72 cell one with 48 cells or A and B model something like this: http://www.asectw.com/Images/flow1.jpg 1- A source provide cells and send it to server ti test it. After testing each cell, it must be transf...